Spending watchdog stresses importance of building on success of London 2102

Regeneration Tue, Mar 22, 2016 5:06 PM

Spending watchdog stresses importance of building on success of London 2102

In a review of the London 2012 Games, the National Audit Office has underlined the success of the Games and stressed the importance of building on that success to deliver the promised legacy benefits.

The report to Parliament draws out some of the widely acknowledged successes of the Games. These include the widely praised opening and closing ceremonies and the 11 million tickets sold for the Olympics and Paralympics combined. LOCOG met the huge logistical challenge of recruiting and deploying 70,000 volunteers and medal targets were exceeded, with the Olympic and Paralympic teams winning 65 and 120 medals respectively.

Since London was awarded the Games in 2005, the Government’s preparations and management of the £9.3 billion Public Sector Funding Package have been led throughout by the Department for Culture, Media and Sport. According to today’s report, there is likely to be a £377 million underspend against the £9.3 billion Public Sector Funding Package, though the final position depends on the accuracy of assumptions about remaining expenditure and will not be known precisely until 2014. The final position is subject to some remaining areas of uncertainty: for example, the final cost of converting the Athletes’ Village, and of settling outstanding contracts with suppliers.

Since the Funding Package was set in 2007, the operational costs within it have increased markedly; most notably, it has had to cover £500 million additional costs for venue security, for which there was originally no provision. However, the Funding Package as a whole has been able to cover these costs.  The final cost of the Olympic Delivery Authority’s programme to build the venues and associated infrastructure is expected to be around £6.7 billion, compared to the £8.1 billion that was originally available to it.

The Cabinet Office now has central responsibility for coordinating and assuring delivery of the legacy, and these new arrangements are a positive step towards maintaining focus and direction after the Games themselves. With numerous organisations responsible for particular aspects of the legacy, the Cabinet Office will need to provide strong leadership to make the most of the momentum created by the success of the Games. While the future use of the Olympic Stadium is still uncertain, most venues and facilities on the Olympic Park now have an agreed long-term use and legacy tenant.

The spending watchdog also recommends that the valuable skills in project management, contracting and risk management gained by officials who have worked on the Games be deployed on other public sector projects.

Featured News

Specification news
FSi Promat launches new EN tested fire stop system for...

Passive fire protection specialist FSi Promat has launched a new slab edge fire stop...

Read More >>

Specification news
James Hardie launches Conceal System for Hardie Panel,...

James Hardie, the world leader in the manufacture of high-performance fibre cement...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Mada ProGuard Brochure Brochure

Mada ProGuard Brochu...
By Magply

Download Now >>

 FIREscape+ Range Overview Brochure

FIREscape+ Range Ov...
By Hochiki Europe (UK)...

Download Now >>

Master Catalogue Brochure

Master Catalogue
By F.H. Brundle

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Woodura® by Bjelin: Real Wood, Reimagined for Specification
Woodura® by Bjelin: Real Wood, Reimagined for Specification

Woodura flooring Planks and Woodura Herringbone from Bjelin are redefining what architects and...

Read More >>

GYPSOTECH® EXTERNA LIGHT Cement board
GYPSOTECH® EXTERNA LIGHT Cement board

Lightweight fibreglass-reinforced cement board, designed to be applied both on the inside and...

Read More >>

Cedral Birkdale
Cedral Birkdale

Cedral - Birkdale fibre cement slate has a smooth surface and dressed edges. It offers a traditional...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Fortitude™ Steel Railing Systems: Adjustable Off-the-Shelf Balustrade Guide
Fortitude™ Steel Railing Systems: Adjustable Off-the-Shelf Balustrade Guide

Fortitude Steel Railings and Balustrades are one of the most versatile, off-the-shelf, steel...

Watch Now >>

Pro-Railing® Stainless Steel Handrail Systems: 6 Modern Balustrade & Glass Railing Solutions
Pro-Railing® Stainless Steel Handrail Systems: 6 Modern Balustrade & Glass Railing Solutions

Pro-Railing® – our Stainless Steel Handrail Component System with six stunning ranges to choose...

Watch Now >>

Why Professionals Choose Outdure QwickBuild | Aluminium Deck Frame Case Study
Why Professionals Choose Outdure QwickBuild | Aluminium Deck Frame Case Study

This case study explores a stunning designer terrace featuring the Outdure QwickBuild system,...

Watch Now >>