Delayed decisions on higher-risk building applications quadrupled

Latest News Tue, Jul 22, 2025 5:55 AM

The Health and Safety Executive (HSE), acting as the Building Safety Regulator (BSR), released data on building control approval applications for higher-risk buildings (HRBs) in England, from October 2023 to March 2025.

Building control approval is a statutory requirement for work on all HRBs and is needed for work to start.

HRBs are those with at least seven storeys; are at least 18 metres high; are a hospital or care home, and/or contain two or more residential units.

The new data shows that delayed decisions on higher-risk building (HRB) applications in England increased by 443% between 1Q2024 and 1Q2025.

The data refers to applications made for building control approval of work on new and existing HRBs.

Building control approval is necessary for HRB projects to pass Gateway 2 – a stop/go point where work on HRBs is assessed against building regulation requirements before it’s allowed to take place.

According to regulation, decisions on building control approval applications for new build HRBs must be made within a 12-week determination period. Decisions for work on existing HRBs must be made in eight.

In the first quarter of 2025, 155 (60.3%) of 257 decisions on applications were delayed. By comparison, 35 (29.9%) of the 117 decisions made in 1Q2024 were delayed.

The jump in delayed decisions appears to have been driven by growth in the BSR’s caseload.

The total caseload in 1Q2025 was more than triple (323%) the caseload in 1Q2024. Meanwhile, the percentage of applications where decisions were made within the determination period, fell from 70% to 33% in the same period.

Dr David Crosthwaite, chief economist at BCIS, said: “Delayed decisions on higher-risk building applications have a wide-reaching and detrimental impact on the construction sector. BCIS expert panellists – cost consultants whose experiences help to inform movement in our tender price indices – have reported that approval delays at Gateways 2 and 3 are having a significant impact, pushing back project starts and putting pressure on resource management.

“Looking at the data, the BSR has not performed effectively since 2Q2024. In most cases, making decisions within the determination period is a statutory requirement and with a growing caseload, the need for process reforms is clear.”

The median time taken for decisions where an application was approved rose from 13.7 weeks in 1Q2024 to 25.1 weeks in 1Q2025.

The only decisions consistently made on time in this period were for invalid applications – those that do not pass the validation process or have been marked inactive with no determination made.

Looking at caseload trends, there were over 1,000 applications still awaiting a decision at the end of March 2025. This was a 451% increase on the backlog recorded at the end of March 2024.

Publication of the data followed the announcement of reforms to the BSR that include a new ‘Fast Track Process’ intended to support housebuilding activity.

This will introduce building inspector and engineer capacity to the BSR to improve the processing and review of existing new build cases and remediation decisions.

Featured News

Specification news
SME home builders blocked by soaring costs and planning...

A new report, Planning for Small Sites, from the Home Builders Federation (HBF) and...

Read More >>

Specification news
Royal visit celebrates Willmott Dixon's sustainable...

Willmott Dixon has received Royal recognition for its groundbreaking sustainable...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Your Specialist Partner in Composite Steel Roof & Floor Decking Brochure

Your Specialist Part...
By RMD Profiles Ltd

Download Now >>

PVC-U System Fully Reversible Windows by Epwin Window Systems Brochure

PVC-U System Fully R...
By Epwin window systems...

Download Now >>

Spectus Bevelled Windows and Doors Brochure

Spectus Bevelled Win...
By Epwin window systems...

Download Now >>

Vertical Sliding Sash Window Brochure

Vertical Sliding Sas...
By Epwin window systems...

Download Now >>

Two-Part Cill System Brochure

Two-Part Cill System
By Epwin window systems...

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

DUOFLEX
DUOFLEX

DUOFLEX is a high quality elastomeric bitumen, hot bonded to the substrate incorporating the fleece...

Read More >>

TECSOUND
TECSOUND

TECSOUND is a polymer based, bitumen-free, high-density synthetic membrane. The combination of its...

Read More >>

ISOLAIR MULTI
ISOLAIR MULTI

ISOLAIR MULTI is a natural and ecological vapour-permeable, windproof and water-repellent thermal...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Discover the Power of Blue Roofs in Urban Flood Management
Discover the Power of Blue Roofs in Urban Flood Management

In this video, we explore how blue roofs are transforming urban landscapes by helping to mitigate...

Watch Now >>

RMD Profiles - UK Experts in Metal Decking, Design Installation
RMD Profiles - UK Experts in Metal Decking, Design Installation

At RMD Profiles, we’re more than just metal decking. From supply-only solutions to full design and...

Watch Now >>

A responsible addition: HIMACS shapes are now SCS-Certified for recycled content
A responsible addition: HIMACS shapes are now SCS-Certified for recycled content

HIMACS has long been the solid surface material of choice for architects and designers looking for a...

Watch Now >>