Huge HS2 bridge move completed four days ahead of schedule

Latest News Wed, Aug 27, 2025 10:49 AM

A specialist HS2 engineering team has moved a 112m long, 1,631 tonne steel structure over a section of Lawley Middleway – part of Birmingham’s ring road, four days ahead of schedule.

The operation was successfully delivered by HS2’s main works contractor in the West Midlands, Balfour Beatty VINCI (BBV) and their bridge move contractor Mammoet.

To minimise disruption to road users, the huge span was moved during night-time road closures - moving between 18 and 24 metres every night using a special skidding system - ensuring that the road has remained open during the day.

From the first day of the move on 15 August, the team - helped by favourable weather conditions, were able to get ahead of programme, meaning the road will be back to normal from 6am on Friday 22 August instead of the planned full reopening on Monday 25 August.

HS2’s Head of Delivery for the Curzon Approaches, Greg Sugden said: “This is a fantastic achievement for the team, and the culmination of two years’ work including detailed design, planning, construction and delivery of this highly technical launch operation.

“It is the first steel structure to be put in place for the one mile stretch of viaducts on the approach to Birmingham Curzon Street Station – a pivotal part of the high-speed railway now starting to take shape.”

Georgios Markakis, Project Manager at Balfour Beatty VINCI said: “This is a proud moment for my team, who have worked hard to deliver this impressive feat of engineering. Through careful planning and expert support from our supply chain, we were able to deliver the operation much quicker than planned.

“Not only have we successfully delivered a milestone feat of engineering on the HS2 project, we’ve also been able to get the road back to normal early – which is good news for everyone.”

Rather than building the bridge in situ, disruption to road users was drastically reduced by constructing the steel span on land next to Digbeth Canal over the last two years. On 15 August 2025, heavy lifting engineering experts Mammoet rotated the bridge 90 degrees using two self-propelled modular transporters (SPMTs).

Over the following four nights, a skidding system - with a jacking push/pull mechanism, was used alongside the SPMTs to move the structure into place across Lawley Middleway. This combination of techniques is rarely used and is a first for BBV on the HS2 project.

Lawley Middleway bridge forms part of the railway’s approach to Birmingham, with high-speed trains travelling out of the west portal of the 3.5 mile Bromford Tunnel at Washwood Heath and onto a one mile stretch of five connected viaducts - Duddeston Junction, Curzon 1, Curzon 2, Lawley Middleway and Curzon 3 which links onto the platforms of Birmingham Curzon Street Station.

Now at peak productivity, work will progress on this section of the railway with the second Bromford Tunnel breakthrough, Curzon 2 viaduct move, first Duddeston Junction Viaduct move, reopening of Aston Church Road, demolition of the old Aston Church Road bridge and start of construction of the new Saltley Viaduct – all set to happen over the next 12 months.

Featured News

Specification news
CIBSE publishes updated guide on the risks of...

CIBSE in collaboration with Arup, Loughborough University and Inkling has launched...

Read More >>

Specification news
Futurebuild 2026 tops 20,000 visitors and takes...

Latest figures from Futurebuild 2026 confirm the new built environment super event -...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Mada ProGuard Brochure Brochure

Mada ProGuard Brochu...
By Magply

Download Now >>

 FIREscape+ Range Overview Brochure

FIREscape+ Range Ov...
By Hochiki Europe (UK)...

Download Now >>

Master Catalogue Brochure

Master Catalogue
By F.H. Brundle

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Woodura® by Bjelin: Real Wood, Reimagined for Specification
Woodura® by Bjelin: Real Wood, Reimagined for Specification

Woodura flooring Planks and Woodura Herringbone from Bjelin are redefining what architects and...

Read More >>

GYPSOTECH® EXTERNA LIGHT Cement board
GYPSOTECH® EXTERNA LIGHT Cement board

Lightweight fibreglass-reinforced cement board, designed to be applied both on the inside and...

Read More >>

Cedral Birkdale
Cedral Birkdale

Cedral - Birkdale fibre cement slate has a smooth surface and dressed edges. It offers a traditional...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Fortitude™ Steel Railing Systems: Adjustable Off-the-Shelf Balustrade Guide
Fortitude™ Steel Railing Systems: Adjustable Off-the-Shelf Balustrade Guide

Fortitude Steel Railings and Balustrades are one of the most versatile, off-the-shelf, steel...

Watch Now >>

Pro-Railing® Stainless Steel Handrail Systems: 6 Modern Balustrade & Glass Railing Solutions
Pro-Railing® Stainless Steel Handrail Systems: 6 Modern Balustrade & Glass Railing Solutions

Pro-Railing® – our Stainless Steel Handrail Component System with six stunning ranges to choose...

Watch Now >>

Why Professionals Choose Outdure QwickBuild | Aluminium Deck Frame Case Study
Why Professionals Choose Outdure QwickBuild | Aluminium Deck Frame Case Study

This case study explores a stunning designer terrace featuring the Outdure QwickBuild system,...

Watch Now >>