BSR sees overall approval rate rise following complex case resolutions

Latest News Wed, Apr 8, 2026 6:24 AM

The Building Safety Regulator (BSR) has released its latest building control Gateway 2 update.

It demonstrates a continuing positive momentum against a backdrop of increasing decisions, improvements from its pilot batching process for applications and a focus on existing remediation projects.

Highlights to 29 March 2026

  • Across all categories, 284 Gateway 2 decisions were made by the Building Safety Regulator (BSR) in the 12-weeks to 29 March, with a 67% approval rate.
  • New applications representing 12,975 residential units were received and applications representing 16,721 units have been determined, of which 10,165 (61%) were approvals.
  • 61% of decisions (19 out of 31) made by the Innovation Unit (IU) in the last 12 weeks were approvals. This means the 12-week rolling approval rate (less invalidations and withdrawals) is significantly up from last month, with a median approval time of 22 weeks.
  • 62% of all decisions across all Gateway 2 categories related to London cases.
  • In the last 12 weeks, 92 remediation decisions were made (49 in London) with an overall approval rate of 61%. This compares to only 228 decisions made throughout 2025.
  • The batching process is outperforming the previous MDT model, delivering initial assessments in support of decisions in a median time of just 4 weeks.
  • Legacy cases have reduced to 2, with 13 long-term cases with significant technical challenges now transferred to a complex case category.

The update demonstrates a continuing positive momentum against a backdrop of increasing decisions, improvements from its pilot batching process for applications and a focus on existing remediation projects.

Charlie Pugsley, Acting Chief Executive Officer of the Building Safety Regulator, said: “We continue to see improvements to numbers of approvals for new build and remediation cases and the time taken to get to a decision.

“The data we have published today reinforces the significant improvements we have seen when you look at where we were in July 2025, with median decision times of 51.5 weeks.

“A big part of our work to drive improvements is now focused on improving technical consistency in the sector and ensuring that learning from challenging designs or applications is shared. So, we have less complex cases to work through, further reducing decision times. This is directly increasing the availability of thousands of safe new and existing homes across England.

“To manage applications – particularly the intense demand we are seeing in London, which accounts for six in ten of our Gateway 2 decisions – our batching pilot is proving highly effective. By collaborating with specialised external engineering suppliers, we are significantly accelerating processing times, while maintaining our rigorous regulatory oversight.

“However, we recognise the need to push further on existing buildings. That is why our remediation improvement plan provides targeted measures to bolster our resources and support industry in submitting higher-quality applications.

“Speed can never come at the cost of safety. Our goal continues to be to ensure industry can construct safe buildings and that residents see the essential safety improvements they deserve.”

Featured News

Specification news
NBS moves HQ to greener city-centre home

NBS (part of Hubexo), the platform for connected construction information, has...

Read More >>

Specification news
PYROGUARD’S TEAM ORANGE SUMMITS YR WYDDFA (SNOWDON)...

Fire safety glass manufacturer Pyroguard has raised over £4,000 for Men’s Minds...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

2026 Product Brochure Brochure

2026 Product Brochur...
By ​The Radiator Compan...

Download Now >>

System for Laying Floor and Wall Coverings Brochure

System for Laying Fl...
By Fassa Bortolo Floors

Download Now >>

Training for Excellence Brochure

Training for Excelle...
By Aico

Download Now >>

The Connected Home Solution Brochure

The Connected Home S...
By Aico

Download Now >>

Safety First, Aico First Brochure

Safety First, Aico F...
By Aico

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Glass Partition Walls
Glass Partition Walls

Partition wall systems made of glass allow transparent room partition. They open, divide and...

Read More >>

FASSAFILL MEDIUM
FASSAFILL MEDIUM

Water repellent cement-based sealant for grouting joints from 2 to 12 mm, resistant to mould and...

Read More >>

FASSA AQUAZIP FAST
FASSA AQUAZIP FAST

Two-component elastic cement membrane, quick drying even at low temperatures, for waterproofing and...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

DAB EsyBox Pop | Compact booster pump for perfect home water pressure
DAB EsyBox Pop | Compact booster pump for perfect home water pressure

Struggling with weak showers and inconsistent flow? The DAB EsyBox Pop is the revolutionary,...

Watch Now >>

Marsh Industries - Phos-Lite
Marsh Industries - Phos-Lite

Marsh Industries - Phos-Lite

Watch Now >>

Marsh Industries - Nutra-Lite
Marsh Industries - Nutra-Lite

Marsh Industries - Nutra-Lite

Watch Now >>