Most major infrastructure and construction projects require intervention to stay on track, NISTA report finds

Latest News Wed, Jul 15, 2026 5:41 AM

The majority (72%) of major infrastructure and construction projects in the Government Major Projects Portfolio (GMPP) in 2025/26 faced significant or major risks to delivery, according to a new annual report from the National Infrastructure and Service Transformation Authority (NISTA).

Of the 68 infrastructure and construction projects in the GMPP in 2025/26, 39 were rated amber (as of March 2026), where successful delivery remains feasible if issues are addressed promptly to avoid a cost or schedule overrun.

A further 10 projects were rated red where successful delivery appears to be unachievable due to major issues with project definition, schedule, budget, quality and/or benefits delivery.

Across all categories in the GMPP, 29 of 189 projects (15%) were rated green, 109 amber (58%) and 34 red (18%). The remaining 17 projects were exempt from ratings.

Image: Lower Thames Crossing - National Highways

“Projects in the GMPP are notoriously complex and challenging to deliver," said Karl Horton, data services director at BCIS. “The high proportion of amber and red ratings reflects that reality rather than any lack of commitment from NISTA or government departments.

“This is particularly true for infrastructure and construction projects. Our latest infrastructure forecast is that civil engineering costs will rise by 15% over the next five years, while tender prices for civil engineering work are expected to increase by 19% over the same period.

“The current cost environment, compounded by heightened tensions between the US and Iran and the resulting pressure on oil prices, is creating significant challenges even for relatively routine projects. Add to that sector-specific issues, such as constrained MEP capacity and planning-related delays, and delivering schemes on the scale of HS2, the Lower Thames Crossing or Sizewell C becomes exponentially more difficult.

“The reset of the GMPP and the decision to concentrate attention on a smaller number of the country’s largest projects should help provide greater clarity and focus. Government departments and NISTA are under significant pressure to ensure the 10-year infrastructure strategy delivers on its promises to the economy. Getting these projects right is absolutely imperative if they are to unlock the growth and wider benefits the UK urgently needs in an increasingly unpredictable world.”

In 2025/26, 42 projects left the GMPP with 26 reporting delivery against their objectives. Projects typically leave the GMPP when successfully delivered or they no longer require NISTA support.

In the last year, eight infrastructure and construction projects left the GMPP, two of which were due to successful deliveries. The remaining six left due to being stopped or brought to an early closure, or because the project no longer met GMPP criteria.

Since April 2026, the number of projects in the GMPP has been reduced to 81 to enable more targeted support for the most nationally significant and highest‑impact UK projects and programmes.

In July, the government also confirmed changes to scrap mandatory pre-application consultation requirements for Nationally Significant Infrastructure Projects (NSIPs), under the Planning and Infrastructure Act. The government expects the reforms to cut up to 12 months from the planning process and potentially save the wider industry £1 billion in this Parliament.

Featured News

Specification news
Recofloor drives circular economy with new flooring...

Recofloor, the UK’s leading vinyl flooring recycling take-back scheme funded by...

Read More >>

Specification news
Linear Living receives green light for Lord Street...

Linear Living has received planning approval for its 24-storey residential scheme on...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Bjelin - Woodura Herringbone Brochure

Bjelin - Woodura Her...
By BJELIN

Download Now >>

Bjelin - Consumer Brochure 2026 Brochure

Bjelin - Consumer Br...
By BJELIN

Download Now >>

Bjelin Accessories Brochure Brochure

Bjelin Accessories B...
By BJELIN

Download Now >>

SEE Building, University of Salford Brochure

SEE Building, Univer...
By Kingfisher Louvre Sy...

Download Now >>

One Berkeley Street, Mayfair, London Brochure

One Berkeley Street,...
By Kingfisher Louvre Sy...

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Woodura® by Bjelin: Real Wood, Reimagined for Specification
Woodura® by Bjelin: Real Wood, Reimagined for Specification

Woodura flooring Planks and Woodura Herringbone from Bjelin are redefining what architects and...

Read More >>

GYPSOTECH® EXTERNA LIGHT Cement board
GYPSOTECH® EXTERNA LIGHT Cement board

Lightweight fibreglass-reinforced cement board, designed to be applied both on the inside and...

Read More >>

Cedral Birkdale
Cedral Birkdale

Cedral - Birkdale fibre cement slate has a smooth surface and dressed edges. It offers a traditional...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Fortitude™ Steel Railing Systems: Adjustable Off-the-Shelf Balustrade Guide
Fortitude™ Steel Railing Systems: Adjustable Off-the-Shelf Balustrade Guide

Fortitude Steel Railings and Balustrades are one of the most versatile, off-the-shelf, steel...

Watch Now >>

Pro-Railing® Stainless Steel Handrail Systems: 6 Modern Balustrade & Glass Railing Solutions
Pro-Railing® Stainless Steel Handrail Systems: 6 Modern Balustrade & Glass Railing Solutions

Pro-Railing® – our Stainless Steel Handrail Component System with six stunning ranges to choose...

Watch Now >>

Why Professionals Choose Outdure QwickBuild | Aluminium Deck Frame Case Study
Why Professionals Choose Outdure QwickBuild | Aluminium Deck Frame Case Study

This case study explores a stunning designer terrace featuring the Outdure QwickBuild system,...

Watch Now >>